I would appreciate information regarding the availability of the following capabilities for the Project Planning tool:
Project timeline traceability, including:
Tracking the original milestone baseline;
Recording any subsequent baseline revisions;
Comparing multiple baselines at the same time;
Export and reporting capabilities, particularly:
Available export formats;
Standard and custom reports;
Reporting options for baseline changes, milestone progress, and timeline deviations;
Reporting multiple baselines on the same report.
Could you please confirm whether these features are currently supported and provide any relevant documentation?
Thanks

Hello @FP, please refer to my answers below:
Project timeline traceability:
Answer: Yes. A baseline can be captured (saved as a snapshot) at a defined point. The baseline preserves the original milestone dates, which remain unchanged when the working plan is updated. You can then compare current plan (including current milestone dates) against the baseline to track the changes.
Answer:Yes. Multiple baselines can be created and retained, and the current plan can be compared against any selected baseline.
Answer: Not supported. The current plan can be compared against any selected baseline. Simultaneous comparison of multiple baselines, or direct baseline to baseline comparison, is not available.
Export and reporting capabilities:
Answer: You can export the project as:
Answer: Standard reports are provided (Summary report with project analytics charts). Project Intelligence (PUS-OC) offers an analytics application for diagnostic and trend analysis of past and ongoing projects.
Answer: Baselines are shown in the schedule view (current plan vs. a selected baseline), not as a separate report. Milestone progress is available in the Summary report, and timeline deviations are visible in the schedule view, where the current plan, including actual dates, can be displayed against a selected baseline.
Answer: Please refer to my previous answer related to comparing multiple baselines.