New task panel in Collaborative Task widget

Hello ENOVIA User Community,

need your help to find an easy solution when a basic platform user (PCS role) is opening a new task using Collaborative Task widget. Due to a very rich input panel, my users tend to fill all fields (especially Planned Start and Planned End) and they always forget to assign the new task to themselves. Moreover, I would like them to provide both an estimated duration and an estimated effort.

 
A customized New Task Panel can surely help, but it seems not possible at the moment (2026x FD04 OC). Other ideas?
 

Tks!


Not sure if my use case is clear: once a new task is opened and then connected to a project, Planned Start and Planned End should be computed by XPP, non forced by users. 
This feature would be very helpful when milestone dates are not defined and simply a rough estimation of planned start/end dates is needed, especially when task priority changes rapidly. Just for reference, Liquidplanner seems to have this capability.

Answers 2
AL
AL 2026-11-15

Not something that you can do out of he box 

MY
MY 2026-11-15

@AA  You could also write a custom Widget 😃