Hello.
How can I handle multiple resource assignments for an operation in the MGA?
For example - need more than one worker for an operation - worker resource needs to be assigned more than once.
I have studied documentation for the Process Planning app and discovered, there is something called "usage".
However, I have not found a way to do this in MGA.
I think I’m supposed to follow this process:
- Define capable resources for operations
- Define a Capable Resource Structure for the Workplan
- Define the Usage for resources inside the Capable Resource Structure
However, the Capable Resource Structure command just creates an empty Area object linked to the Workplan and does not take into account previously defined Capable Resources. Am I supposed to fill the Area object with the resources manually?
What is the process I’m supposed to follow?
As far as I know, there is no documentation or training for this.