Hello,
I have a question about reusing existing operations in new workplans.
Use case:
Customer has standardised operations, that always take the same time and use the same resources.
Question is:
Should they make copies of these operations or should they just reuse those existing ones?
As far as I know, items implement links exist on Workplan level that has a link to an MBOM structure. Therefore a single operation can be used in multiple workplans and implement different items in each of them.
The only problem would be work instructions. As far as I know, operation needs to be in an In Work state to be available for work instructions authoring.
How is this supposed to be handled?