Concurrent Process Planning

Am I allowed to revise / duplicate a BOP while keeping existing MBOM and BOR structure and implement links intact?

In my scenario, product and resources are not changed but only process planning. So I don’t want to create a new revision of MBOM and BOR. However, I want to carry existing implement links and be able to modify them where necessary. Otherwise, it would be exhausting and risky to create all implement links all over again.

The problem is, I lose all implement links between the new BOP and existing BOR after I revise existing BOP. Is there a way to carry BOP – BOR links to the new revision of BOP?