Hello.
I am considering how to take advantage of the simulations created in Ergonomics At Work Apps.
One of the things we looked at was the playback time of the simulation.However, the playback time was quite different from the actual work time.
In the simulation I created, detailed tasks (such as handing out playing cards) had a large discrepancy from the actual work, while large movement tasks (moving cardboard) had a small discrepancy.
・I can change the speed on a motion basis for each activity, but is it possible to speed up the overall speed and shorten the playback time?
・Is there any way to use the simulation playback time to streamline the review of the factory's production operations?
We would like to expand the use of this Apps beyond body load analysis.
If you have any good use cases, please advise.