I have an assembly which requires ~800 rivets. Currently, I am rebuilding the assembly to be more stable. lowering the resolution, moving mates down the assembly tree, etc. Would it be "cheaper" to mate as many rivets as possible or are patterns the way to go? Purely asking from a computer resources standpoint.
Thanks!

mates are more ressource heavy. The graphic part could also become intense, so perhaps having a display state with the rivets hidden and one with the rivets shown would be profitable on the long run.
unless it is very important to show the count of the rivets I would leave them off. When I would have projects that required special bolting it was a pain to add all the bolts but it helped with getting an accurate count for that job.
Other jobs, where we could use standard bolts from bins we where able to leave off those kind of things and models ran smother than adding 1000's of fasteners.
The other option is to use the hole wizard and that sketch can be used as the sketch pattern for the other rivets once the first one has been added.