I know you can have different projects run at the same time, IE two solvers running at once, but what about one solver finishes, then another begins? I have two projects with nearly identical criteria, except the port locations for the fans differ. I want to run one solver, than another after that one is finished. it will take roughly 12 hours for both to complete and I will not be here to manually start the next one, but I would like it to run overnight so I have results in the morning.
Any suggestions?
SolidworksFlow Simulation