In my previous organizations ECO releasing with the planned date of release so that all RDE, Designers, Reviewers etc will stick that plan and they proceeding for Release activity but in V6 2013x OOTB I observed ECO - There is No Planned and Actual Target Release Date,
ECO can be released as user wish/date, I mean there is no control over ECO release duration,
we can set Route for users and reviewers but there is again no control over the track of Late ECOs.
Is there is Relationship between Part target Release date and ECO? how to get notifications in case of Delay in ECO release?
Can we configure Planned/targeted date of Release and Actual Released date for ECO?
Thanks,
Anil