Rejected Task on Change Action Approval tab

#TASK TASK Hello, 

I performed the following steps: 

  • Change Action promotion from In Work >> In Approval
  • Rejection of the generated Task in the Approvals tab --> Change Action automatically demoted to In Work 
  • Again Change Action promotion from In Work >> In Approval
  • Now the generated Task was approved --> Change Action moved to Completed 

My question is: why does the Approval tab of the Change Action still show the Rejected Task instead of the Task that actually allowed the completion of the Change? Is this behavior the normal functioning of the Platform?