For changes in the project plan, the What-If analysis is available under the "Experiments" tab. This works well.
However, it also happens that the PL has to define certain dependencies and conditions in the project schedule. If there a conflict occurs because of these dependencies and task contraints, there should be a hint about this schedule conflict.
Scenario:
Milestone MS02 has constraint date "Must finish on".
Task 215 has a dependency on MS02 with FS +0 d and the end date is before Milestone MS02.
Now the End Date of Task 215 changes to a date after the milestone and creates a conflict. But the change is still applied, with no indication of it, either in color or as a message.
Expected behavior: Message or alert with indication of the conflict, and a choice for 'apply' or 'discard'.
Is there some kind of configuration to get such a message or a hint?
