Hi everyone,
I have a question about time reporting in XPP.
With DPM, I can fill in a daily timesheet for each resource and generate labor reports with the effort recorded by each person.
Can the same be done in XPP?
So far, the only way I have found to report effort is to enable Override Duration with Effort and then update the Actual Effort field.
However, this has some limitations:
- the effort is cumulative rather than daily;
- I have to manually update the total effort each time;
- the effort is tracked at the task level, not by individual resource.
Is there a way in XPP to record daily timesheets for each resource assigned to a task, similar to DPM?
Thank you,
Simona
