We have a question about 3DExperince DELMIA and Apriso integration. For the car manufacturing, we have the process below.
┌───────┐
│ Start │
└───┬───┘
┌─────────────┴─────────────┐
▼ ▼
┌─────────┐ ┌─────────┐
│ Process1│ │ Process3│
└────┬────┘ └────┬────┘
│ Good │ Good
▼ ▼
┌─────────┐ ┌─────────┐
│ Process2│ │ Process5│
└────┬────┘ └────┬────┘
│ Good Good │
└───────┐ ┌─────────────┘
▼ ▼
┌─────────┐
│Process4 │
└────┬────┘
│ Good
▼
┌─────────┐
│Process6 │
└────┬────┘
▼
(Next)Imagine an automotive assembly process in which the left door assembly and right door assembly are manufactured independently and subsequently joined in a common assembly operation.
The process flow contains both splits (parallel branches) and joins (synchronization points). At a join point, multiple predecessor operations exist, and the successor operation must not be started until all predecessor operations have been completed.
We received the following explanation:
In 3DEXPERIENCE DELMIA, it is possible to model a join in the process flow. However, the join behaves as an OR-join, meaning that the successor operation can be released as soon as any one of the predecessor operations is completed.
It is not possible in 3DEXPERIENCE DELMIA to define an AND-join condition, where the successor operation can be released only after all predecessor operations have been completed.
Therefore, the process definition must be transferred from DELMIA to Apriso, and the synchronization logic for the AND-join must be implemented on the Apriso side.
Is this understanding correct?