Hi,
I am the person in our company that handles PDMW upgrade/updatesand issues. We will be upgrading to Solidworks 2009 soon and Iwould like some information about the proper way to go about it.Can the server software be upgraded to 2009 and still have installsof SW 2008 running and checking out/in files from it? Can theserver software still be 2008 and can installs of Solidworks 2009be checking out/in files from it without problems? What is theproper order of upgrading/updating to a new version of Solidworks?We have the PDMW server software running on our separate Networkserver and just a few Soldworks software seats all currentlyrunning 2008. Thanks.
-TimSolidworksWorkgroup Pdm
I am the person in our company that handles PDMW upgrade/updatesand issues. We will be upgrading to Solidworks 2009 soon and Iwould like some information about the proper way to go about it.Can the server software be upgraded to 2009 and still have installsof SW 2008 running and checking out/in files from it? Can theserver software still be 2008 and can installs of Solidworks 2009be checking out/in files from it without problems? What is theproper order of upgrading/updating to a new version of Solidworks?We have the PDMW server software running on our separate Networkserver and just a few Soldworks software seats all currentlyrunning 2008. Thanks.
-TimSolidworksWorkgroup Pdm

With that said, you should install the vault and client on a testmachine first to get familiar with any settings that are new. Makenotes or take screen shots of these settings to use as a guide whenyou setup for real.
I install clients first and then go and upgrade my Vault Server.After the new Vault service is started, you may log each clientinto the Vault. Verify all is well before saving any files in 2009.
Note: depending on the number of seats you have you may want to dothis during a planned long weekend. You can upgrade the vaultfirst, but older clients won't be able to use the newer Vault untilthe newer client has been installed.
is this true?
if not how do you accomplish this?
UPDATE -
according to the SW Knowledge Base, this used to be possible, butthe VAR says its no longer possible:
Solution Id: S-01789 Area: FAQ
Question: Can SolidWorks 2005 be used with PDMWorks 2006 withoutupdating the SolidWorks seats if just the PDMworks 2005 seats areupdated?
Answer: Yes, SolidWorks 2005 will be able to work with PDMWorks2006. Download the PdmWorks 2006 Sp1.0 server download and updatethe 2005 Pdmworks vault. When the PDM clients log into the vaultthey will be updated up to PDMworks 2006
I read in the PDMworks Help that after PDM 2009 and SW 2009 areinstalled I need to convert vault files to 2009 using SW Taskscheduler. I'm not familiar with this, where specifically do I findthis?
You can do this with the SW Task Scheduler and have it run atnight. I would do it one project at a time. Be sure that you backup your vault before you start this process.
There is a seperate discussion group for the Task Scheduler. Youshould find information there to help you with this.