This is about a success story relative to one of our Customers who radically transformed its ability to answer to market demand thanks to DELMIA Ortems.
Context & key objectives for the project :
- Get an industrialized scheduling system to respond to demand in a complex and constrained environment
- Improve ability to answer to short term demand variability
- Reduce finish good, packaging and ingredients supply chain stocks
- Manage complex scheduling constraints: sanitation's during the night, changeovers, production lines balancing, freezing tunnel, etc.
- Share production schedule between shop floor, procurement and other departments
Achieved Value :
- Simplified, optimized and automated planning process
- Planning Time Fence (PTF) reduced to 5 Days
- Finish good, packaging and ingredients supply chain stocks reduced to 5 Days
- Increased orders visibility to more than 3 Months
- Mid Term Stock coverage follow-up at any time
- Changeover times considered and optimized automatically
I wanted to share this success story with our Community Members.