I make a lot of large assembly drawings that require a lot of item balloons. My problem is I must build my assemblies based on pre-existing BOMs that have established item numbers (I cannot allow Solidworks to assign its own numbers as the drawing must match the BOM). Is there a way for me to import my established BOM so my balloon numbers will match, or must I continue to use the balloons as text (which can become labor intensive when I have a drawing requiring 100+ balloons.)