Hello everyone,
Is there any way to revise the PR that needs to be modified? As a test, I used the Change Action. After adding the PR into it, I noticed that only the PR was affected by the change.
What I aim to implement is to revise the PR along with the OP, STEPs and resources associated with it. (on 3DDashboard).
Do I need to add all of them to the Change Action for this purpose? If I include all of them, will the new revision create the same structure in the updated version?
In one of my tests, I had to bring last revision of OP and STEP manually with using "replace by new revision" option.
Is there a process you can recommend regarding this?
Thanks in advance!