Extend effectivity of a mfg. Item instance with a new Mfg. Plan and working under CA with CA Applicability Date

Dear all,

Imagine the following use-case:
one Mfg Assy with 2 Provided Parts (A and B)
the A is having the effectivity MFG Plan 01 --> Infinite
the B is having the effectivity MFG Plan 01 or Mfg Plan 02

The following Mfg. Plans are available: Plan 01, Plan 02, Plan 03 and Plan 04.

How the Effectivity of Provided B can be extended as: MFG Plan 01 or Mfg. Plan 02 or Mfg Plan 04 < (mfg. Plan 04 --> Infinite)
using the CA Applicability Date? (Provided part B is not available within Plan 03)

In Prod. Str. Editor, there is a command called Extended Evolution Effectivity that can be used to manage this use-case.
(The extended effectivity defined by the change action's Applicability is now applied to the selected instances in the structure)

Can this use-case be covered with DELMIA Native App (PST or PPL) or Manufacturing Widget?

Thanks for support.
Any advice is welcome.