Hi,
I created a crane using the “Define Crane System” command as a transfer tool.
Can this crane be used as a resource pool for a Load activity?
When I try to set it up, the crane successfully delivers the product. However, it’s supposed to perform a Load activity afterward and then continue with the next transfer from another resource.
The issue is that the resource with the Load activity remains in a “Waiting for Resource” status until the end of the simulation.
Do you have any idea what might be causing this, or how to correctly configure the crane as a shared resource for Load activities?
Thank you,